Activities to Accomplish Project / Timeline

April 11,1999 Filled out paperwork and decided on topic.

May 9, 1999 Discussed topics by completing project title, overview, and

objectives.

July 6, 1999 Completed goals, timeline, list of activities to accomplish

project, implementation strategies, and evaluation procedures.

July, 1999 Worked on History of Nekoosa.

Compiled information on services and organizations of Nekoosa.

Organized extra- curricular activities that exist within the school.

Decided on maps of Nekoosa and surrounding areas to be used.

Calender of Nekoosa and surrounding area activities.

July 22, 1999 Discussed and checked over completed information on the

surrounding area. Made a list of items needed for the seminar.

July 25 - 29, 1999 Teaching the Transescent XIX Seminar

August 16, 1999 Attend new student orientation to acquire more ideas. Plan

information that will be shared with staff.

August 19, 1999 Explain project overview to staff.

August, 1999 Complete team information to hand out to new students.

1999-2000 Gather new information for 2000 update. Distribute

information at new student orientation